Scope: Additional Space to Meet Demands for New and Existing Programs
Projected Cost: $16 million
Actual Cost: $11,447,320
Architect: Corgan
General Contractor: Cadence McShane
Square Footage: 44,090
Scope: Fine Arts Addition to Address Space Equity with Other FISD High Schools
Projected Cost: $700,000
Actual Cost: $775,702
General Contractor: Reeder General Contractors, Inc.
Square Footage: 2,000
Scope: Expansion to Increase Capacity to 2,100 Students Like Other High Schools
Projected Cost: $4 million
Projected Cost: $3,431,194
Architect: Stantec
General Contractor: Core
Square Footage: 4,791