Panther Creek High School

  • Original Bond Cost: $122.5 million

  • Final Cost: $131.4 million

  • Architect: Corgan

  • General Contractor: CORE

  • Square footage: 389,694

  • Opened Fall 2022

Wilkinson Middle School

  • Original Bond Cost: $43 million

  • Final Cost: $57.6 million

  • Architect: Corgan

  • General Contractor: Joeris General Contractors

  • Square footage: 159,400

  • Opened Fall 2023

Elementary School #45

  • Original Bond Cost: $28 million

  • Revised Bond Cost: $32 million

  • Project on hold

Wortham Intermediate

  • Original Bond Cost: $45 million

  • Final Cost: $53 million

  • Architect: Huckabee

  • General Contractor: CORE Construction

  • Square footage: 142,640

  • Opened Fall 2023

Land for Future Schools

  • Original Bond Cost: $22 million

  • Final Cost: $13.2 million